Saint John Proactively Manages a Critical Raw Water Main Using Advanced Robotics Inspection Tech
Saint John, NB, Canada
The City of Saint John provides raw water for industrial customers delivered via a 1500 mm and 1350 mm (60-inch and 54-inch) pipeline. Managing the integrity of this critical main is key to maintaining continued operation and production for major industrial plants in the region.
Topics Covered
Funding
General Fund/Existing Public Funds
Project Status
Operational since 2017
Problem Addressed
In the spring of 2017, one of the City’s industrial customers scheduled a maintenance shutdown limited to four days.
During the shutdown, the City’s priority was to gather visual and actionable information on the current condition of the Industrial Water Main that services the plant, last inspected five years previously. The short four-day time frame and configuration of the pipeline made it difficult to dewater, and for safety reasons, precluded a conventional manned visual inspection.
Solutions Used
Beginning in April of 2017, and under the inspection of CBCL Limited, the City’s consulting engineer for this project, the City engaged Xylem to perform an electromagnetic condition assessment and visual inspection on 8.2 kilometers of the line.
This was the second condition assessment that Xylem has performed on the main (the first was conducted in 2012), which is constructed of prestressed concrete cylinder pipe (PCCP), wrapped with high strength steel pre-stressing wires that provide support to the structural integrity of the pipe. An electromagnetic inspection identifies and locates broken wire wraps, an early indicator of pipe deterioration. Broken wire wraps can be caused by physical damage to the pipe, corrosion, or hydrogen-induced cracking. The visual inspection identifies other signs of deterioration such as corrosion staining, mortar deterioration, and joint deficiencies.
The condition assessment was performed using Xylem’s tethered PureRobotics™ platform, equipped with electromagnetic technology and a high-definition CCTV camera that delivers and records a live video stream from inside the pipe. In this case, the robotic platform was selected because of the profile of the line and the difficulty of fully draining, which precluded a manned or free-swimming tool approach.
Outcomes
1
The survey was conducted in less than four days, well within the shutdown window.
2
PureRobotics™ condition assessment identified 20 pipes with broken wire wraps including 3 pipes with new distress since the initial baseline inspection conducted five years previously
3
City now has actionable data regarding the condition of the pipeline.
Something Unique
This project required an around-the-clock inspection because of the short 4-day shut-down window
Who Should Consider
Any client with a time-sensitive inspection window, or a client with a pipeline configuration that makes it difficult to dewater, or a configuration that makes it difficult for a manned visual inspection.
Last Updated
Jan 8th, 2020Keywords